Problem/Challenge
Fast Delivery
Miniature precision parts have long posed a problem to customers with
short delivery requirements. The demanding tolerances and small feature
size have meant CNC and EDM were the tool building options of choice.
Conmed, a leader in patent monitoring systems needed injection molded
parts for its new Connector design in less than two weeks and was
looking for a solution other than CNC and EDM.
Solutions/Results
Rapid Tooling
General Patterns 24/7 operation and our hybrid tooling construction
(Laser Sintering and High Speed milling) was used to produce a tool
in 12 days that met critical dimensions of +/-.001 on features as
small as .015 wide. 24/7 injection molding and a three hour guaranteed
sampling program allowed General Pattern to produce 50 polycarbonate
parts 2 days ahead of the promised delivery date.
Benefit/Impact
FDA Testing
With parts in hand, Conmed was able to complete its assembly and maintain
its scheduled delivery to the FDA for product testing and subsequent
approval. Failure to meet this milestone could have lead to a 6 month
delay in Conmeds new product release.
Commercial
Tool Price $5,300
Unit Price $1.25 each (polycarbonate)
Performance 12 Days
|